Coordination Meetings will be posted on this site as well as notifications to subs by email.
JR Stephens presented metal casework options to the design team on 02/15/12 at the weekly construction meeting. 1st floor measurements were also taken for casework and if subs have any questions or need JRSCO on site please send requests to Ray. The casework submittal was loaded on the submittal FTP site and mechanical subs notified for their use.